Aug, 2010: Start to build the Parabolic Trough concentrator
Oct, 2010: Start to build the Linear Fresnel concentrator
Jan, 2011: Completed the first group of 150 meters Trough concentrator
Mar, 2011: Completed two groups of 96 meters Linear Fresnel solar concentrators
Jun, 2011: The first group of Parabolic Trough system produced steam
Jul, 2011: Start to build the second group of Trough concentrator
Oct, 2011: Completed 2nd group of 150 meters Trough concentrators installation
Dec, 2011: Start to install oil tanks,heat exchangers and other auxiliary equipment. Connected all the pipes
Mar, 2012: Filled all the conductor oil into the system
Apr, 23, 2012: Built up Concentrated Solar Thermal Demonstration Park
May, 9, 2012: Parabolic Trough and Linear Fresnel Concentrated Solar Power system generated power successfully and connected to Grid